Liquefied Natural Gas

Venture Global seeks a larger CP2 LNG export terminal

The filing would add six liquefaction blocks, a new gas-fired power plant and a third marine berth in Cameron Parish. It also seeks more compression on the CP Express Pipeline from Jasper County, Texas, and opens a June 30 intervention deadline.

2 min read·422 words·View source
Venture Global seeks a larger CP2 LNG export terminal
1 / 3
Photo by Diego F. Parra on Pexels

Venture Global is asking FERC to approve a bigger CP2 LNG export project in Cameron Parish, Louisiana, along with new compression on the CP Express Pipeline from east Texas. The notice starts the public review clock and gives outside parties until June 30 to intervene.

  • Venture Global wants to expand CP2 LNG in Cameron Parish, Louisiana.
  • The plan adds six liquefaction blocks and new pipeline compression.
  • The pipeline would run from Jasper County, Texas, to the terminal.
  • FERC’s notice opens the intervention window for the proposal.
  • Venture Global is asking the Federal Energy Regulatory Commission, or FERC, to let it enlarge its CP2 liquefied natural gas, or LNG, export project in Cameron Parish, Louisiana

is asking the , or , to let it enlarge its , or LNG, export project in . The plan would add six more liquefaction blocks at the terminal and widen the industrial footprint of a project that is already under construction.

The request reaches beyond the shoreline site. is also seeking approval for new compression and related facilities on the , which runs from Jasper County in east Texas to the terminal on the east side of the Calcasieu Ship Channel. For people along that corridor, the proposal means more gas infrastructure tied to the same export chain.

Six more liquefaction blocks

Liquefaction is the step that chills natural gas into a liquid so it can be loaded for export. Adding six blocks would increase what can process and ship overseas if regulators sign off.

That is the real-world shape of the filing: more equipment, more power needs and more industrial activity around the terminal, not just a paper change in the project description.

The Texas side of the build

The pipeline request is part of the same larger expansion. Venture Global wants new compression on CP Express, the kind of infrastructure that helps push gas over distance to feed the terminal.

The companies filed the application on May 26, 2026, and the published June 12 also sets the intervention deadline for outside parties. For Gulf Coast communities and east Texas towns along the route, the filing is a reminder that depend on a long chain of wells, pipes, compressors and terminal hardware.